Home › Forums › Discussion › Baseline work not visible in Task usage view › Reply To: Baseline work not visible in Task usage view
Hi – Looks like you have updated the work field or assigned resources to the tasks after baseline the plan. Also, check the baseline fields in Baseline table of Gantt Chart. If the baseline work is 0, my guess is right. Then, you need to redo baseline the project and then record the actuals.