Reply To: Error with inactivating tasks with 0% complete

Home Forums Discussion Error with inactivating tasks with 0% complete Reply To: Error with inactivating tasks with 0% complete

#77601
Sai Prasad
Participant
  • Community Leader
  • Forum Pro

I doubt your question is Project displays error when inactivating in progress tasks or completed tasks – see http://i.imgur.com/zoAJeUS.png. This is usual, as in progress tasks can be cancelled rather reset the remaining work of the task to 0. If you are receiving an error message even for 0% tasks it looks peculiar. Can you throw more light on its predecessor/successor % completion or send a screenshot of the error message with the portion of the file