Remove the “remaining” planned work/planned cost as if you were performing a baseline change, then mark the task 100% complete. That is, the effort completed will reflect the cost/work at the 50% progress.
If you *are* using baseline change management at your organization, prepare a spreadsheet showing the before and after change (% complete, cost, work) and use Notes to comment the history. You might then be able to assign the task’s remaining budget to another task.