Loading...
Quick Links

Reply To: How to Inactivate a task with Progress in Microsoft Project 2007

Home Forums Discussion How to Inactivate a task with Progress in Microsoft Project 2007 Reply To: How to Inactivate a task with Progress in Microsoft Project 2007

#96850
Josh LoganJosh Logan
Member

Remove the “remaining” planned work/planned cost as if you were performing a baseline change, then mark the task 100% complete. That is, the effort completed will reflect the cost/work at the 50% progress.

If you *are* using baseline change management at your organization, prepare a spreadsheet showing the before and after change (% complete, cost, work) and use Notes to comment the history. You might then be able to assign the task’s remaining budget to another task.