Reply To: 99% completed project when all tasks are 100%

Home Forums Discussion Forum 99% completed project when all tasks are 100% Reply To: 99% completed project when all tasks are 100%

#29256
Jerry Insall
Participant

I know it can happen when a resource is assigned to a roll-up task in the schedule, but you can only apply a budget resource to the zero level task.