Reply To: Active Directory Sync – Identifying users from resources

Home Forums Discussion Active Directory Sync – Identifying users from resources Reply To: Active Directory Sync – Identifying users from resources

#6286
Community
Keymaster
Hi Bill:
Here at QC, we use AD sync targeting a special AD User Group to populate Enterprise Resource Pools membership.  Just because a user is a resource, that doesn’t mean he/she is a user to access project server.
In the latter case, we utilize project user groups (also sync with other AD user groups) to control actual access to project server.
Long story short, when a person a listed as an ACTIVE resource, it doesn’t automatically grant the person the access to project server.
Hope this helps.  You can also contact me at jyin@qualcomm.com for further questions.
Best, Joseph