Reply To: approved and unpubished project task time

Home Forums Discussion approved and unpubished project task time Reply To: approved and unpubished project task time

#6011
Avatar photoCommunity
Keymaster
Yes.  In PWA, do the following:
1.  Click on Task Updates.
2.  Click on the drop-down Go-To list.
3.  Choose Applied Requests and Errors.
4.  You will get a listing of all accepted / rejected task updates.
5.  There is a column that indicates published Y or N.
6.  You can click on any row to view the actual details from the resource’s entry for the project/task.
Best wishes,
Tom H.