Hello Chiquita,
If you are using Timesheet tracking in Project Server 2010, you define the categories for administrative time under Server Settings -> Administrative Time.  The categories that you define will be available on the Timesheet for the team member.
There is also the option to use Line Classifications for things such as travel time, on-site support, etc. if you have different billing rates for the same task.  You define line classifications under Server Settings -> Line Classifications.
~Ginger Drehmel
Project Manager/Business Analyst
Globe Education Network