Reply To: BCWP calculation issues MSP 2007

Home Forums Discussion BCWP calculation issues MSP 2007 Reply To: BCWP calculation issues MSP 2007

#6746
Community
Keymaster

I’m seeking confirmation that there is a known bug in MSP 2007 BCWP calculation.  I have the Calculation Option for Earned Value set to [Physical % Complete].  BCWP appears to be calculating correctly (=[Physcial % Complete]*[Baseline Cost]) at the  resource level, yet the BCWP at the task level is incorrect and not equal to the roll-up (sum) of resources.  This is only true for in-process tasks, but not for every in-process task.

Thanx,  Dennis