Reply To: Calculating Cost Based on Cost Rates from Project Server 2010 Reporting Database

Home Forums Microsoft Project Discussion Forum Calculating Cost Based on Cost Rates from Project Server 2010 Reporting Database Reply To: Calculating Cost Based on Cost Rates from Project Server 2010 Reporting Database

#6772
Avatar photoCommunity
Keymaster

As a workaround, you can use assignment work and cost to calculate the hourly rate.  This will only work if you are using single entry mode as you need to protect assignments from being deleted.  Hopefully someone will have a better answer that doesn’t require custom code.  Otherwise I agree with the previous answer provided.