Hi Martin,

Welcome to this Microsoft Project forum:)

Try it and see!  You didn’t tell us which version of Project you’re using, but from the Print Preview window select Page Setup.  In the dialog, select the Header (or Footer) tab.  Click the drop down arrow next to Project Fields, and select he custom field (eg Text1) in which you have put your version info, and then Add/OK.  That should do it!

FAQs, companion products and other useful Project information can be seen at this web address:  http://project.mvps.org/faqs.htm

Hope this helps – please let us know how you get on 🙂

Mike Glen
MS Project MVP (97-11)
See http://tinyurl.com/2xbhc for my free Project Tutorials