Sai: We tried your macro. It does perform as you indicated. Unfortunately, our leadership team was hoping to be able to see in a Task Usage view, at a glance, what months a resource has bandwidth as they view across the table.
I’m surprised that whatever calculation and coding used to produce “red” when an overallocation exists, can’t also produce “green” when an underallocation exists. Oh well, maybe in a future version.