Reply To: Changing duration in 2010

Home Forums Discussion Changing duration in 2010 Reply To: Changing duration in 2010

#6493
Community
Keymaster
The settings under File > Options > Schedule will only be taken into account for the newly created tasks. You’ll have the change the duration type for the already existing tasks ‘manually’ (like suggested using the Type column).