Reply To: Clarify the Process of Transitioning from Custom Fields in Stand Alone 2010 ro Project Server 2010

Home Forums Microsoft Project Discussion Forum Clarify the Process of Transitioning from Custom Fields in Stand Alone 2010 ro Project Server 2010 Reply To: Clarify the Process of Transitioning from Custom Fields in Stand Alone 2010 ro Project Server 2010

#6714
Avatar photoCommunity
Keymaster

Jeffrey,

Enterprise fields are not the same fields so they would need to be converted manually.  You can paste the entries into Project Server but it is still manual process.  Then you would import the project (preferred method) which will again force you to re-assign the custom fields to the equivalent enterprise field values.

Hope that helps…Larry