Reply To: Close Tasks to Updates

Home Forums Discussion Close Tasks to Updates Reply To: Close Tasks to Updates

#7075
Community
Keymaster

Laurel,To close the project summary task (top level task in the timesheet), you need to select task 0 in the close task to update and then publish. It seems like you’ve done this and it doesn’t work. Is this a problem with just this one project or all projects?The ability to add a task to a project is user permission that you can turn off if you want (create new task or assignment). This assumes you aren’t using this feature as a normal process with real projects.I don’t have any other suggestions for why the close task doesn’t work for the top level task.Larry