Reply To: Cost Accrual for Costs Incurred per Minimum 12 or 24 Hour Day

Home Forums Discussion Forum Cost Accrual for Costs Incurred per Minimum 12 or 24 Hour Day Reply To: Cost Accrual for Costs Incurred per Minimum 12 or 24 Hour Day

#6748

Thanks for your reply.  The calendar used doesn’t seem to matter.  If there is a partial day the resource is still pro-rated.  This normally occurs on the first day and last day of the project, but can sometimes occur during the project as well.