Larry Thanks a Bunch. I am using MS Project 2010, and I tried to create external links using the followng steps
I created a folder called Prototype:
I created 2 MPP files in that folder.
One was called a “Program File”.
The second file was called a “release plan”
In order to create an external link I did the following:
In the “program file” I created a Task called “Tollgate Review” (The same name task as the predecessor)
Then I clicked on the “information” icon,
Clicked in Predecessor
in the ID: I Typed ” release plan<ID no of the task>
In the predecessor it does show “External Link” but when I clicked “ok” nothing happens.
Do I need to do something else? or am I missing a step?
Thanks