Reply To: Create a Master Plan that automatically retrieves Milestones from other projects

Home Forums Discussion Forum Create a Master Plan that automatically retrieves Milestones from other projects Reply To: Create a Master Plan that automatically retrieves Milestones from other projects

#10606
Velu Rajanbabu
Keymaster

This was great I got it work, but last question. When I link the tasks, an identical task is created in both the linked files. One of the tasks is greyed out (the one that is updated) and the other task  shown as  tasks shows up in both the files, one is greyed out and the other task has the predecessor link, but the start and end date is the default date. My question is:

How do you just have one task i.e. updated task in the Master Plan & the Actual Task (task linked) in the predecessor Plan shown in the plan.

I want to baseline the Master plan so that I can track them. Can that be done with only the “Greyed Tasks” in the Master Plan.

 

Thanks