Home › Forums › Discussion Forum › Create task dependencies (links) across projects › Reply To: Create task dependencies (links) across projects
Hi Tony,
Welcome to this Microsoft Project forum:)
I don’t have a definitive answer for you. However, when working with multiple projects, Project is prone to such problems when the individual projects are in difernt folders. Try moving all the files into a single folder. If not, make sure the full path to the file is recorded for the link. If you’re not sure, try linking again as you did in a tempory file that you know works, then examine the exact path that Priject used – copy the link and try again.
FAQs, companion products and other useful Project information can be seen at this web address: https://project.mvps.org/faqs.htm
Hope this helps – please let us know how you get on 🙂
Mike Glen
MS Project MVP (97-11)
See https://tinyurl.com/2xbhc for my free Project Tutorials
“