Reply To: Delete or remove calendar(s) from a template

Home Forums Discussion Delete or remove calendar(s) from a template Reply To: Delete or remove calendar(s) from a template

#21778
Jon Roberts
Guest

Hello,
I misused the term “template”.  The client has in fact sent me a .mpp file that they call a “template”.  I have followed suggestions from others like, deleting all resources and re-entering them.  Once I re-enter the resources, back come the calendars.  Since these are resource calendars, they do not show up when one uses the Organizer.

I have taught and used MS Project since 1998, and much to my surprise, in Project 2010 Professional, when I add a resource of any sort to the Resource Sheet in a new blank file, that resource’s name shows up on the list of Calendars in the Change Working Time list along with Standard, 24-hour and Night Shift.  Of course, when one saves the file as a .mpt, there is no option to delete unwanted/unneeded calendars.

This is one of the most interesting/challenging little battles that I have had with Project in quite some time.

Regards,

Jon Roberts, MCT, MCTS (Managing Projects with MS Project 2007, 2010 & 2013)