Reply To: Disappearing views when migrating to MSP2010

Home Forums Microsoft Project Discussion Forum Disappearing views when migrating to MSP2010 Reply To: Disappearing views when migrating to MSP2010

#6484
Avatar photoCommunity
Keymaster
Hi Shaun
No, I am not connected to a server. I was able to locate the problem, but I don’t have a solution yet. I have a lot of custom bar formats in my views. When I reduce that list drastically to only a few very basic ones, the view is displayed in MSP2010. I was not able yet which feature it is exactly which causes the problem, I spent hours removing individual bar formats.