Reply To: Displaying Remaining Work and Remaining Cost across time

Home Forums Discussion Displaying Remaining Work and Remaining Cost across time Reply To: Displaying Remaining Work and Remaining Cost across time

#9837
Avatar photoCommunity
Keymaster
Hi Rich,
To the best of my knowledge, this cannot be displayed in the MSOP Usage Grids.  You might try to export the work and actual work values using the analyze timescaled data in excel and do the math there.  It would be nice to be able to see remaining work and cost by month in project.
Cheryl