Posted by Asim AnsariWhen a duration of a task is 1 day, MS Project and the task has dependency and on Auto Schedule, MS Project is not consistent in the way it has the Start date and Finish date. Example:
Task Name
Duration
% Complete
Start
Finish
Task 1
1 day
0%
Mon 4/2/12
Tue 4/3/12
Task Name
Duration
% Complete
Start
Finish
Task 2
1 day
0%
Tue 3/6/12
Tue 3/6/12
How can you Fix this problem and make it Start and Finish Dates in a consistent manner (Task 1 or Taks2), and why is it MS project doing this?