 Posted by Asim AnsariWhen a duration of a task is 1 day, MS Project and the task has dependency and on Auto Schedule, MS Project is not consistent in the way it has the Start date and Finish date. Example:

Task Name Duration % Complete Start Finish
Task 1 1 day 0% Mon 4/2/12 Tue 4/3/12

 

Task Name Duration % Complete Start Finish
Task 2 1 day 0% Tue 3/6/12 Tue 3/6/12

How can you Fix this problem and make it Start and Finish Dates in a consistent manner (Task 1 or Taks2), and why is it MS project doing this?