Reply To: Duration and scheduling

Home Forums Discussion Duration and scheduling Reply To: Duration and scheduling

#10522
CommunityCommunity
Keymaster

You might want to check you default calendar settings to make sure you are working standard hours (8 AM to 5 PM).  I would also suggest checking your project options to toggle the task type between fixed work and duration to see if that makes a difference.  If neither of those fix the issue, then I would suggest looking at the details of each of the two tasks to see if the settings are the task level are different (ie one is effort driven, one uses a different calendar, etc.).