Reply To: Duration Calculation Bug?

Home Forums Discussion Forum Duration Calculation Bug? Reply To: Duration Calculation Bug?

#6124
I have Project 2007 and on step two if you apply the resource at the same time you will get a different result than if you apply them one after the other.  Project keeps track of the order the resource is applied when making its calculations.
When you set the value to 0 hrs of work, then make the change back to 80hrs, the resources are already applied to the task, so Microsoft Project splits the work evenly between both resources.
Hope this helps….
John Riopel