There are a couple of pieces that you might check to make the Earned value works correctly, you MUST have a baseline, even in the Master Plan which is not going to be there by default. Secondly you must also have a Status Date entry for the Master Plan, since Earned Value reporting bases the calulations from the Status Date, not the current date.
Provide more details after checking these, thanks.