Reply To: Fixed Duration Task with multiple resources assigned – Task % Completed not reflecting the value

Home Forums Discussion Forum Fixed Duration Task with multiple resources assigned – Task % Completed not reflecting the value Reply To: Fixed Duration Task with multiple resources assigned – Task % Completed not reflecting the value

#6796

Hi Larry:

We are on SP1 with June 2011 CU in our PS 2010 environment.  I agreed with you that % COMPLETED should at least have some values since resouces did report progress even if just one of them.  The odd part was that if RES A puts 50% and RES B puts 30, then the % COMPLETED will take the lower value.  % Work Completed is showing the correct aggregate in my case.

I will try this out with FIXED WORK and FIXED UNIT typed tasks too.  Once I completed my testing, I will post to the community on my findings.

Best, Joseph