Reply To: Fixed Duration with Expanded Start-Finish Dates?

Home Forums Discussion Fixed Duration with Expanded Start-Finish Dates? Reply To: Fixed Duration with Expanded Start-Finish Dates?

#3727
Community
Keymaster
Steve,
I do not understand your question I’m afraid.
Duration IS the time between start & finish…
Do you mean effort of 100 hours spread over a period of 2 to 3 months? That’s what the Work field is for.