Reply To: Fixed Duration with Expanded Start-Finish Dates?

Home Forums Discussion Fixed Duration with Expanded Start-Finish Dates? Reply To: Fixed Duration with Expanded Start-Finish Dates?

#6413
CommunityCommunity
Keymaster
you assign a resource either reduce units or specify the amount of work you want. So over 4w 80h of effort is units of 50%