Reply To: Formatting Critical Milestones

Home Forums Discussion Formatting Critical Milestones Reply To: Formatting Critical Milestones

#7016
Community
Keymaster

Hi, remember that bar styles are applied in order, so once can overwrite the other.  It is possible to change the Shape type from Solid to Outline, which will give you what you want.  The colour can also be changed.  Remember, you will need to apply the formatting in each view you want it to be shown in.  The graphic below shows how I have set up the milestones in the default Gantt Chart view (note in this view the Critical Task T1 is not shown in Red, however it would be on the Tracking Gantt.)