Try this:
The Project Holiday Import Wizard is a tool for marking national and religious holidays as non-working days in the Microsoft Project base calendars (versions 2002-2007). The holidays are sourced from the Holiday File installed with Microsoft Outlook, which contains over 8,000 holidays for 88 countries. If you don’t have Outlook installed, the wizard will take you to a page where you can download the file. The selected holidays are imported into the base calendars of the chosen project plan document or the global template. The tool is easy to use and best of all, it’s free! project-holiday-import-wizard
Mike Glen
Project MVP (97-11)