Reply To: how to link this task ?

Home Forums Discussion how to link this task ? Reply To: how to link this task ?

#6825
Community
Keymaster

Cepi,

This question has come up before and I’m not sure there was a satisfactory answer given out of box functionality.  If you don’t get a better answer you could setup two tasks for create artwork, one for each country.  The first task takes that becomes current controls the start date of the artwork.  It’s a poor mans solution but will communicate the need appropriately.