Reply To: How to resolve issues with Project Professional Cache

Home Forums Microsoft Project Discussion Forum How to resolve issues with Project Professional Cache Reply To: How to resolve issues with Project Professional Cache

#6050
Avatar photoCommunity
Keymaster
This Cache issue can also be created by closing the project desktop tool to quickly after you check in and close your project schedule.  The check in feature submits a job to run in the queue.  If you close your desktop tool using the RED X in the upper right hand corner before the queue job finishes then the project will be stuck in cache mode.

-Richard Theisen