Keymaster

Roy, great suggestion that made me think.  I love to figure out cool ways to solve unique issues.  Here’s another way that might be a bit easier.  Select every task in your project (multiple easy way of doing this) and select the Task Information option (Shift+F2 is the shortcut).  Under the General tab, select the checkbox for Rollup.  This will roll all Gantt bars to the project summary task (make sure you are showing the project summary task).  This will show you all gaps between tasks.  Hope this helps…