Hey Joe you’re in luck. From MS Project, go to the Resource Usage view, view the timescale area by month, and select the Detail Styles. Not sure what version you are on but right click the detail styles area and then select Detail Styles. From there you can add rows like Unit Availability, Remaining Availability, and others. Have fun checking it out…