Home › Forums › Discussion › Importing actual hours fm Excel into Proj Pro 2010 › Reply To: Importing actual hours fm Excel into Proj Pro 2010
You will need to hav a 3 worksheet workbook, one for tasks, one for resources and one for assignments. Try exporting a project with tasks, resources and assignments to see the structure. It’s better not to import dates as these set constraints against tasks which is counter-productive.