Home › Forums › Discussion Forum › Importing actual hours fm Excel into Proj Pro 2010 › Reply To: Importing actual hours fm Excel into Proj Pro 2010
Definitely would require custom coding via the PSI (Project Server Interface), but you should be able to pull or feed Project Server 2010 with Timesheet data.
https://msdn.microsoft.com/en-us/library/ee767706.aspx
Note this bullet for “What the PSI Does”:
Jim