Definitely would require custom coding via the PSI (Project Server Interface), but you should be able to pull or feed Project Server 2010 with Timesheet data.
http://msdn.microsoft.com/en-us/library/ee767706.aspx
Note this bullet for “What the PSI Does”:
Jim