One of our templates has a task “Get approval from x, if needed”. Let’s say this is task 10. Task 9 is it’s predecessor, and Task 11 is it’s successor. For Task 11, we added 9 as an additional predecessor (9,10), so project managers don’t have to think about changing the link if they inactivate the task (10).