Reply To: Inactivate Task problem

Home Forums Discussion Inactivate Task problem Reply To: Inactivate Task problem

#10553
Community
Keymaster

The only time I run into this if I’ve opened a file previously saved in a compatible format.  I actually just resave it as a Project file, don’t even have to close out, and the inactivate button is active. File, Save As, same name with format of Project; overwrite existing file.