Reply To: Inactivate Task problem

Home Forums Microsoft Project Discussion Forum Inactivate Task problem Reply To: Inactivate Task problem

#6324
Avatar photoCommunity
Keymaster
Christine,
Tasks that contain actual work cannot be inactivated.  Could this be the problem?
Larry Christofaro
Digineer