Reply To: Inactivate Task problem

Home Forums Discussion Inactivate Task problem Reply To: Inactivate Task problem

#6328
Community
Keymaster
Christine,
Now moving to the realm of comical…:-).  One more try.  Could the projects that you are having trouble with have been created using Project Standard.  Inactive tasks are not available in Project Standard.  I only have the Pro version so I don’t know what happens if projects are created and opened between versions.  In my opinion it should work if you are using Pro, but I honestly can’t think of anything else.
Keeping my fingers crossed…
Larry Christofaro
Digineer