Reply To: Insert Column disabled

Home Forums Microsoft Project Discussion Forum Insert Column disabled Reply To: Insert Column disabled

#6513
Avatar photoCommunity
Keymaster
I have not heard of this problem.  I have seen some issues regarding if the file was from an earlier level you can not access some of the fields.  For example, if the file was 2007 you will not be able to use the manual scheduling function in 2010.
Could this be the problem.  When you say some of the files, are the ones that are not working from earlier levels?  Can you insert any column or just not specific ones?