Reply To: Issue, risk, and document icons in PWA

Home Forums Issue, risk, and document icons in PWA Reply To: Issue, risk, and document icons in PWA

#10049
Community
Keymaster
It is not recommended to "remove" the risk list from the project workspace.  This will cause queue sync and reporting issues.  Best practice is to revise the out of box risk list to include your additional fields/functions (and don’t delete out of box fields from the original list).  Are you experiencing issues with what you have done?
Larry Christofaro