We’re using Project 2010 standard version. I think what your saying is that if we collapse parts of the project that their resources don’t get leveled. We just went through 2 months of scenario analysis with 49 versions of the project, 8000-11000 tasks each and I was only leveling certain resources. When leveling with part(s) of the project collapsed, does it still take into account the resources for all tasks when it’s leveling the non-collapsed tasks? Thanks for the updates! JB