Reply To: Multiple Task Dependency Type Selection

Home Forums Discussion Multiple Task Dependency Type Selection Reply To: Multiple Task Dependency Type Selection

#6540
Avatar photoCommunity
Keymaster

You are confusing task typing and dependency relationships.

Relationships are finish-to-start which says that when one task is completed, the next task will start

Task type of fixed duration means that there is a set duration for a task.  (double click on a task, advanced tab to change)

One has nothing to do with the other.