Reply To: Progress Lines in MS Project 2010

Home Forums Discussion Forum Progress Lines in MS Project 2010 Reply To: Progress Lines in MS Project 2010

#19730
Sai Prasad
Participant

Ismet – I need clarity on Edits to total task % complete will be spread to the status date check box. I set the status date two weeks later than current date and updated the % complete of a task that starts today. I don’t see the actual work of the task spread till the status date. Am I missing anything here.

Thanks, Sai