Reply To: Progress Lines in MS Project 2010

Home Forums Discussion Forum Progress Lines in MS Project 2010 Reply To: Progress Lines in MS Project 2010

#19833

Hello Sai,

This is how it works:

Project Options | Advanced | [ ] Edits to total task % complete will be spread to the status date

Initial schedule: img838.imageshack.us/img838/3108/beforeck.png

Now select the checkbox for the related option and re-enter the percent complete values.

Project Options | Advanced | [x] Edits to total task % complete will be spread to the status date

Modified schedule: img35.imageshack.us/img35/8940/afterb.png

Regards, Ismet

PS. Sorry for the links instead of embedded images…