Hello Sai,
This is how it works:
Project Options | Advanced | [ ] Edits to total task % complete will be spread to the status date
Initial schedule: img838.imageshack.us/img838/3108/beforeck.png
Now select the checkbox for the related option and re-enter the percent complete values.
Project Options | Advanced | [x] Edits to total task % complete will be spread to the status date
Modified schedule: img35.imageshack.us/img35/8940/afterb.png
Regards, Ismet
PS. Sorry for the links instead of embedded images…