Reply To: Progress Lines in MS Project 2010

Home Forums Discussion Forum Progress Lines in MS Project 2010 Reply To: Progress Lines in MS Project 2010

#19836
Sai Prasad
Participant

Hello Ismet,

Thanks for the details. It works.

If  Edits to total task % complete will be spread to the status date is checked, I wanted to know

a) which cases should this option be checked?

b) In https://imageshack.us/photo/my-images/341/91828140.png/ the 5 days task with 40 hours is scheduled before the status date and is set to 50% complete. Before this option is cleared, the 50% is divided as 20%, 20% and 10% with actual work as 8 hours, 8 hours, 4 hours. If this option is checked, the 50% is divided as 10% for all the 5 days with the actual work as 8 hours, 8 hours, 4 hours. This looks odd as how can we say the task is 10% complete on each day by the work is 8 hours per day.

Regards, Sai