Reply To: Project 2010 false-positive notifications to team members

Home Forums Discussion Project 2010 false-positive notifications to team members Reply To: Project 2010 false-positive notifications to team members

#6743
Community
Keymaster

As you mention, this can be controlled by unchecking the box for when my assignments are modified” under personal Settings. Leave the checkbox on for “New tasks are assigned”. This should work, in stopping emails about existing assignments, and still send out emails for new tasks. If this is not working, you might have other issues that might be existing.Project Server August 2011 Cumulative Update, does fix part of the issue by stopping emails for “Completed Assignments”.I also remember Project Server Experts had an article sometime ago on customizing the SQL database o modify these alerts. “