Reply To: Project Pro 2010 Units calculation working incorrectly

Home Forums Discussion Project Pro 2010 Units calculation working incorrectly Reply To: Project Pro 2010 Units calculation working incorrectly

#7113
Community
Keymaster

Doing more checking around, apparently this is standard 2010 functionality and the correct Units calculation is stored in Peak field. Little frustrating that both Peak and Units fields are not both visible in Task form.